Saturday, March 12, 2011

Completion photos

late post - but better than never!









Wednesday, May 26, 2010

Latest photo updates (26/05/2010) from our prof!

Friday, May 21, 2010

Status update - 10/05/2010
The roof extended over the champa tree, walls raised till the roof structure

What sort of behaviour is this! - the team





The team -

Top row from left to right - Mr. Body-builder, Mr. Japanese translator turned eco-builder, Ms. Astro-physicist, Ms. Poi expert + traveller + earth builder, Mr. Sound engineer turned permaculturist and Ms. Interior designer on leave

Bottom row from left to right - Mr. Architect, Ms. Travelling permaculturist, Ms. Exhibition designer, Ms. Soon-will-be architect, Ms. Nature enthusiast, Ms. Youngest of the team

Team bonding!! ;)

Wednesday, May 5, 2010

What sort of behaviour is this - The team!!! Introductions - better late than never!

Our Mad professor!

The architect!!

This man is responsible for teaching us to play in the mud, be confident about it, start mud-fights and ya, catch and throw! By the end of this apprenticeship, we have ready, a fully trained throwball team! Not to mention our developed strength in selective-hearing techniques (about what he said in particular) so we don't lose our minds completely!
And yes, he is responsible for choosing the mad-people team and starting the Lazy list!

Crazy man!

And here is a photo to illustrate
"follow the leader"
- theme of the workshop!! :)
Cobbing Day 8

Walls almost up....
And it poured!!
Cobbing Day 7 -
Saving the construction from the rain.

Obvious concerns -
Why build something that will wash away with rain?
Do these earth walls need such protection always?

Clarifications -
The rain causes harm to the construction when it pours from the top and is prone to seeping in, making it vulnerable at some point. The earth construction - Cob type walls need to be protected till they dry, plastered and sheltered by a roof.
In case of rain from the side, the clay content in the cob gets saturated fast and does not let the water percolate into the wall. Here, the thickness of the wall plays a very important role in its strength and capacity to withhold rain-attacks.
So, these tarpaulins won't be required after the construction is over!!!
Cobbing Day 6

Tuesday, April 27, 2010

News article in the Pune Mirror today - 27th April, 2010

http://www.punemirror.in/index.aspx?page=article&sectid=2&contentid=20100427201004270004355396ad0f613&sectxslt=
The bamboo structure (in progress) for the live roof
Cobbing Day 3
Cobbing Day 2
Cobbing Day 1
Waterproofing
Random rubble masonry for the plinth
Foundation with stone and soil

Stone dust bed

Excavation of site
Excavation till soft stone bed
Plan of construction -

As per the design specifications listed by the 2nd and 3rd standard students of Aman Setu, the construction consists of two classroom spaces - one enclosed and the second like a veranda.
The veranda has a champa tree and space around to sit and learn, chat, play and have fun. hrough the veranda one can enter the enclosed classroom which has circular windows to sit in and lots of space to learn and interact.
Both these spaces are sheltered by a self-sustaining live roof.
In totality, the total construction area is 15' by 45-60'

Introduction to the site